Jackson’s Data Center Ban Now Runs to April 4, 2027. The Ordinance That Would Replace It Is Still Not Written.
The council killed a repeal bid 5-2 on Nov. 17, leaving Saxum’s 230-acre Forest Avenue rezoning frozen. The city attorney has been drafting the replacement rules since summer.
Jackson’s pause on data centers survived its first real test on Nov. 17, and it now has a hard end date: April 4, 2027. The City Council voted 5-2 to reject an ordinance by Ward 3 Councilman Kenneth Stokes that would have repealed the moratorium adopted July 14, according to the Jackson Association of Neighborhoods recap of the meeting (jxnneighborhoods.com). Stokes and Ward 1 Councilman Ashby Foote voted to lift the ban.
The ban was written as 183 days, which would have ended Feb. 12. WLBT reported on Nov. 2 that because the July vote was not published until October, the clock runs to April 4 instead. That is roughly 135 days from today, and it is the deadline that now governs the only data center application on file in the city.
That application belongs to Saxum Investment Group LLC, which is seeking to rezone about 230 acres along Forest Avenue Extension, south of Forest Avenue between I-220 and Medgar Evers Boulevard, near the Ashley Acres and Presidential Hills neighborhoods. The land is currently zoned R-1 residential, C-3 commercial and I-1 light industrial. Saxum’s attorney, Robert Ireland of Watkins and Eager, asked the Planning Board in May to hold the case until the city had a data center ordinance in place, and the board postponed it to a June 24 hearing.
The replacement ordinance is the piece nobody has seen. Interim Chief Administrative Officer and City Attorney Drew Martin told WLBT on Nov. 2 that he was still drafting it and had hoped to finish that weekend. Council President Vernon Hartley said the public will get meetings before any vote. Martin said hearings are unavoidable because the ordinance amends the zoning code. No draft has been released, and no hearing date has been announced.
The arithmetic of the delay is the story. The moratorium has run about 129 days since July 14, and the city has produced no published draft in that time. If the ordinance lands in December, it still needs a Planning Board review and at least one public hearing before the April 4 expiration, which leaves the council a window of a few weeks, not months, to act before the ban lapses on its own.
What the ban does not do is settle Saxum’s rezoning. The moratorium blocks the city from accepting, processing or approving data center permits, zoning map amendments and building permits, per WLBT’s account of the July ordinance. The Forest Avenue application is therefore parked, not decided. If the council lets the moratorium expire without passing rules, the application returns to a Planning Board with no data center standards to apply.
The money at stake has been argued in public but never quantified in a document the Wire could read. Foote has said a data center could add millions to the city’s general fund, according to Mississippi Today’s coverage of the July vote. Opponents, including Environmental Advocates Mississippi’s Natalie Speaks, told a June 25 council hearing that state incentives give data centers large tax exemptions for few permanent jobs, MPB reported. Neither side has produced a city-specific revenue or cost estimate in the record reviewed for this article.
The politics have been loud. On Nov. 3 the council recessed after a dispute over Stokes’s repeal ordinance, and WJTV reported the exchange turned personal. On Nov. 17 the council censured Stokes 6-1 over remarks at that meeting, with Stokes the lone no vote, according to the neighborhood association recap. The repeal then failed two weeks later with Foote and Stokes in the minority.
What’s next: the next regular City Council meeting is Tuesday, Dec. 1, at 10 a.m., and the next Hinds County Board of Supervisors meeting is Dec. 7. Watch the council agenda packet posted at jacksonms.gov for a data center ordinance, and watch the Planning Board calendar for a hearing notice on the Saxum rezoning. The hard deadline is April 4, 2027, when the moratorium expires unless the council extends it or replaces it with adopted rules. Residents who want a say can comment at the council’s public hearings once a draft is released; no date for that hearing has been set.