Development tracker

The Pipeline

Every development project, bond, rate case, and ballot question the Wire is tracking in metro Jackson, with the dates that will decide them. Read this to see what is coming before it is announced.

Projects tracked

13

Dates on the calendar

8

Next decision

Nov 3, 2026

Jackson voters decide a 0.5% prepared-food tax increase and a 1% lodging tax increase for Visit Jackson, the first change since 1983.

Projects, by stage

Under construction

Amazon Web Services data center campuses

Developer
Amazon Web Services
Where
Madison County, with related sites in Ridgeland, Clinton, and Warren County
Money
About $25B disclosed
Status
Construction is under way. A 25-year water and wastewater agreement with Ridgeland, effective March 18, 2025, sets Amazon's peak-day draw at 82 percent of the city's total use and routes 1.8 million gallons a day of cooling wastewater into Jackson's West Bank interceptor.
What's next
Whether JXN Water and Ridgeland put a shortage-priority clause in writing.

Museum Trail: downtown connector, Lakeland Drive bridge, extension to Jackson State

Developer
Jackson Heart Foundation, Greater Belhaven Neighborhood Foundation, Great City Mississippi Foundation, City of Jackson, MDOT
Where
GM&O Depot on East Pearl Street north to LeFleur's Bluff; planned west to Jackson State
Money
About $10M identified: $1.6M original trail, $213K Eastover leg, $588K federal planning grant, $8M bridge ($5M federal); excludes the downtown connector, whose cost is unconfirmed
Status
The Capitol Green Connector downtown is expected to finish construction in October 2026 after an earlier spring-or-summer target, and the $8 million pedestrian bridge over Lakeland Drive broke ground Aug. 19, 2026. The 2.5-mile western extension to Jackson State has a planning grant, and the Wire found no construction money on the record.
What's next
Completion of construction on the downtown connector, then a construction funding source for the leg to Jackson State.

Opening soon

Jackson Rubbish Landfill reopening and fee ordinance

Developer
City of Jackson Public Works
Where
6810 I-55 South Frontage Road, Byram
Status
The Class I rubbish site closed in 2024 when its cell exceeded permitted capacity. MDEQ accepted the construction certification for the new cell in February 2026, and the city said in late September it could reopen any day. An ordinance introduced Sept. 22 replaces the $5-per-cubic-yard rate with $10 a ton for residents and $20 a ton for commercial and out-of-city users.
What's next
Council adoption vote on the fee ordinance, and the publication of the tonnage and cost study behind the rates.

McNair Davis Planetarium reopening

Developer
City of Jackson; operated by the Mississippi Museum of Art
Where
Downtown Jackson
Money
$23M renovation
Status
The city transferred operations to the Mississippi Museum of Art in July 2026. Reopening was expected about six months later, once digital screens go in.
What's next
Reopening in early 2027.

Approved

Prado Vista and the Madison County Conference Center

Developer
Gabriel Prado (private); Madison County (venue)
Where
77 acres off I-55 near Sunnybrook Road, Ridgeland
Money
$100M private, plus $48M county urban renewal bonds
Status
Supervisors authorized the $48 million bond issue for an 1,800-person conference center on a 3-2 vote on Sept. 8, 2026, over objections about the land appraisal and a $10 conveyance clause. The private side adds a 250-room hotel and four restaurants.
What's next
Bond sale and a public construction schedule.

UMMC Cancer Center and Research Institute

Developer
University of Mississippi Medical Center
Where
State Street across from the UMMC campus, Jackson (per Mississippi Today; parcel not announced)
Money
$250M: $100M state capital funds, $125M private campaign (80% raised), UMMC bonds for the balance
Status
The Legislature appropriated $100 million in the FY2027 budget signed in April 2026; private gifts passed 80 percent of the $125 million goal with Regions Bank's $2.5 million this week. A five-story, 250,000-plus-square-foot building aimed at a National Cancer Institute designation, with clinics, infusion suites, clinical trial space, and research labs. No retail component in any plan the Wire found. WJTV reported construction starts in late October and the complex opens in about four years.
What's next
Groundbreaking in late October, with the first public site plan.

Vieux Carre expansion and medical office building

Developer
Vieux Carre Apartments South LLC, an affiliate of State Street Group
Where
I-55 North frontage road south of Meadowbrook Road, Jackson
Money
$28M, with $1.3M in city TIF bonds
Status
The council approved three actions on the project's tax-increment financing agreement on Aug. 25, 2026, clearing the way for construction to start. The plan renovates the 1968 complex, adds 84 units on the 4.8 acres rezoned R-4 in 2021, and builds a 10,000-square-foot medical office building.
What's next
Visible site work on the south parcel and the first building permits, within the 18-month construction window.

Hinds County criminal justice facility

Developer
Hinds County Board of Supervisors
Where
Hinds County
Money
Funded in part by a 1.5-mill tax increase (about $2.3M a year)
Status
Supervisors adopted the FY2027 budget on Sept. 10, 2026 with a 1.5-mill increase, and the new jail is the single largest reason the county gave for needing the money.
What's next
Design, site, and total cost have not been made public.

Proposed

Prado AI off-grid campus

Developer
Prado AI / Gabriel Prado
Where
Undisclosed Jackson-metro site
Status
The Public Service Commission declined to issue the declaratory ruling Prado sought in Docket 2026-AD-10, calling the request premature. Mississippi Power and Entergy Mississippi intervened.
What's next
An off-grid generation permit application, which both utilities oppose.

Undecided

Former Department of Public Safety headquarters site

Developer
State of Mississippi (Department of Finance and Administration)
Where
1900 East Woodrow Wilson Avenue at I-55, Jackson
Status
The 1976 tower was imploded Oct. 4, 2026 after DPS moved to a $70 million headquarters in Pearl. Commissioner Sean Tindell floated a hotel or mixed-use project serving the hospital district; the Department of Finance and Administration will decide, and no proposal has been announced.
What's next
A Bureau of Buildings appraisal, notice, or legislative authorization for the land.

Stalled

Saxum data center rezoning

Developer
Saxum Investment Group (New Jersey)
Where
About 230 acres along Forest Avenue Extension, northwest Jackson
Status
The city's planning director said rezoning hearings will keep being postponed until Jackson adopts data center regulations. The 183-day moratorium passed July 14, 2026 took effect a month later, and the replacement ordinance was still undrafted in mid-September.
What's next
An ordinance, or the moratorium's expiration in February 2027 with nothing to replace it.

Pipeline coverage

Development

The Museum Trail Is About to Reach Downtown. Here Is What Six Miles of Path Could Mean for Jackson Property, and Why It Is Not Atlanta’s BeltLine.

The Capitol Green Connector between the GM&O Depot and Hal & Mal’s is expected to finish construction this month, an $8 million bridge over Lakeland Drive broke ground in August, and planners want the trail to run from Jackson State to LeFleur’s Bluff. The identified money so far is roughly $10 million, not counting the connector. A May 2026 study counted $14.2 billion in private investment along Atlanta’s BeltLine.

October 6, 2026 · 9 min read

Development

UMMC’s $250 Million Cancer Center Is Expected to Break Ground This Month. Nothing on the Record Says the Stadium Has to Go First.

Mississippi Today has described the five-story Cancer Center and Research Institute as located on State Street across from the medical center, with construction starting in late October and an opening about four years out. No plan the Wire could find includes retail. Here is everything on the record about the building, the money, and the land.

October 4, 2026 · 8 min read

Development

The DPS Tower Is Gone. What Happens to the Corner Is Undecided.

The state imploded the 50-year-old Department of Public Safety headquarters at I-55 and Woodrow Wilson Avenue on Sunday morning. It has announced no plan for the land. Nearby, UMMC’s $250 million cancer center is about to break ground, and a 60,000-seat stadium’s future is tied to it.

October 4, 2026 · 5 min read

Economy

Jackson’s Landfill Reopens at $10 a Ton. For Most Loads That Is a Price Cut, and It May Not Cover the Cost.

The council’s new weight-based fee schedule reads like an increase. Run the arithmetic on the old volume-based rate and a pickup load of debris gets cheaper. Mississippi already has the lowest landfill fees in the country, and the last cell filled past its permit in 2024 with no replacement ready, which kept the gate shut for the better part of two years.

September 25, 2026 · 6 min read